Sample bill of quantities (materials list) for a 3 bedroom house in Zambia
What a bill of quantities is
A bill of quantities (BOQ) is a priced list of everything needed for a job: each item, its unit, how much, the rate and the amount. Owners use it to compare quotes, to plan payments and to check what a builder orders.
This page shows the format for materials only. A BOQ for tendering also has labour, roofing, finishes, plumbing and electrics, and should be prepared by a quantity surveyor or engineer.
Sample materials list, in building order
| Item | Description | Unit | Quantity | Rate (K) | Amount (K) |
|---|---|---|---|---|---|
| A. The concrete base in the ground | |||||
| A1 | Cement 42.5R (all concrete) | bags (50 kg) | 94 | 178 | 16,732 |
| A2 | Quarry dust (concrete) | m³ | 7.0 | 480 | 3,360 |
| A3 | Quarry stones (concrete) | m³ | 7.0 | 435 | 3,045 |
| A4 | Anti-termite chemical | litres | 14 | 300 | 4,200 |
| Subtotal A | 27,337 | ||||
| B. Walls up to the floor level | |||||
| B1 | 6 inch concrete blocks | blocks | 1,720 | 9.5 | 16,340 |
| B2 | Cement 32.5N (mortar, plaster) | bags (50 kg) | 37 | 172 | 6,364 |
| B3 | Building sand (mortar, plaster) | m³ | 7.5 | 320 | 2,400 |
| B4 | Brickforce | rolls (10 m) | 31 | 20 | 620 |
| Subtotal B | 25,724 | ||||
| C. The floor | |||||
| C1 | Cement 42.5R (all concrete) | bags (50 kg) | 109 | 178 | 19,402 |
| C2 | Quarry dust (concrete) | m³ | 8.0 | 480 | 3,840 |
| C3 | Quarry stones (concrete) | m³ | 8.0 | 435 | 3,480 |
| C4 | Gravel backfill under the floor | tonnes | 64 | 100 | 6,400 |
| C5 | Conforce wire, 3 mm (2.4 m x 48 m roll) | rolls | 2 | 1,800 | 3,600 |
| C6 | Black polythene under the floor (2 m x 100 m roll) | rolls | 1 | 700 | 700 |
| C7 | Anti-termite chemical | litres | 7 | 300 | 2,100 |
| Subtotal C | 39,522 | ||||
| D. The walls | |||||
| D1 | 6 inch concrete blocks | blocks | 3,300 | 9.5 | 31,350 |
| D2 | Cement 32.5N (mortar, plaster) | bags (50 kg) | 70 | 172 | 12,040 |
| D3 | Building sand (mortar, plaster) | m³ | 14.0 | 320 | 4,480 |
| D4 | Brickforce | rolls (10 m) | 74 | 20 | 1,480 |
| Subtotal D | 49,350 | ||||
| E. The concrete band on top of the walls | |||||
| E1 | Cement 42.5R (all concrete) | bags (50 kg) | 9 | 178 | 1,602 |
| E2 | Quarry dust (concrete) | m³ | 1.0 | 480 | 480 |
| E3 | Quarry stones (concrete) | m³ | 1.0 | 435 | 435 |
| E4 | Y12 steel bars | bars (12 m) | 13 | 153 | 1,989 |
| E5 | Triangle rings | rings | 200 | 9 | 1,800 |
| E6 | Tying wire | kg | 4 | 40 | 160 |
| Subtotal E | 6,466 | ||||
| F. Smooth cement coat on the walls | |||||
| F1 | Cement 32.5N (mortar, plaster) | bags (50 kg) | 53 | 172 | 9,116 |
| F2 | Building sand (mortar, plaster) | m³ | 9.5 | 320 | 3,040 |
| Subtotal F | 12,156 | ||||
| Total materials | 160,555 | ||||
Quantities include a 10% allowance and are rounded up as you buy them. Each part is rounded on its own, so this total is a little higher than the quick estimate on the 3 bedroom guide. Concrete is 1:2:2 with 42.5R cement, quarry dust and quarry stones. Prices used (typical Zambian mid-range, October 2026, kwacha): 6 inch block K9.50, 32.5N cement K172 a bag, 42.5R cement K178 a bag, building sand K200 a tonne, quarry dust and stones K300 a tonne, Y12 bar K153, triangle ring K9, tying wire K40 a kg, gravel K100 a tonne, conforce K1,800 a roll, brickforce K20 a roll, polythene K700 a roll, anti-termite K300 a litre.
How to use a list like this
- Compare quotes: ask each supplier or builder to price the same items and quantities.
- Pay in stages: each lettered part is a stage you can buy and pay for on its own.
- Check the site: if more cement, sand or stones are used than the list allows, ask why before more is delivered.
What this estimate does not include
These figures cover the foundation, floor, walls and plaster only, and only the materials. They do not include:
- the roof (iron sheets or tiles, timber trusses, fascia)
- doors, windows, burglar bars and ceilings
- plumbing, electrics, tiles, paint and fittings
- builder and labour payments, transport and offloading
- the plot, plans, council approval and a wall fence
Roofing, finishes and labour often cost as much as the materials above, so always get quotes for them before you decide on a budget. BuildAudit Zambia does not estimate the roof yet.
Free quick calculator
Pick the size closest to your house. This is the same engine as the full app, using typical prices.
Questions
What is a bill of quantities (BOQ)?
A bill of quantities is a list of the items and quantities needed to build something, with a rate and an amount for each. A full BOQ prepared by a quantity surveyor also includes labour, roofing, finishes, plumbing and electrics.
Is this sample a full BOQ?
No. It is a materials-only list for the foundation, floor, walls and plaster of a 3 bedroom house, laid out in BOQ style. Use it to understand the format and to check a builder's list. For tendering, ask a quantity surveyor or engineer.
Can I get a list like this for my own plan?
Yes. Enter your house size, or take a photo of your plan, in the free BuildAudit Zambia app and it builds the list for you in kwacha.